Construction Schedule (As on: 30-June-2018)

Corridor Number Corridor Details
Corridor 1 Miyapur to LB Nagar
Stage 2 Miyapur to SR Nagar
Stage 5 SR Nagar to LB Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

Project Updates

Stage TOTAL KMS TOTAL PIERS TOTAL STATIONS
Stage-1 8.01 15 7
Stage-2 11.96 456 10
Stage-3 8.25 305 6
Stage-4# 11.47 440 10
Stage-5 17.31 652 17
Stage-6* 9.66 373 9
Total 66.60 2541 59
Stage TOTAL PIERS Actual TOTAL Actual VIADUCT Actual IN STN % KMS
Stage-1 315 315 245 70 100% 8.01
Stage-2 456 456 356 100 100% 11.90
Stage-3 305 305 245 60 100% 8.25
Stage-4# 440 399 300 99 100.0% 10.26
Stage-5 652 652 482 170 100.0% 17.31
Stage-6* 373 354 266 88 94.9% 9.13
Total 2541 2481 1894 587 97.6% 64.86
Casting Yard Casting Yard Name Scope No. Segment Cast Nos. Cast%
1 Uppal 16500 15195 92.09%
2 Qutubullahpur 8423 8423 100.00%
Total 24923 23618 94.76%